Project:
Slabs to Tarmac Framework Contract
We have been appointed by Nuneaton & Bedworth Borough Council on a 3 year term tender, which involves the upgrading of existing slab footpaths in sheltered housing complexes to asphalt surfacing. The works require detailed design input with regards to footpath layouts and drainage solutions. As part of the framework, we have also installed a number of disability access ramps and driveways under the Disabled Facility Grant.

Contract value
Client:
Nuneaton & Bedworth Borough Council
Completion Date:
Ongoing
Project:
COVID-19 Emergency Social Distancing Measures
Following the COVID-19 lockdown, emergency social distancing measures were immediately put into place in local town centres to ensure social distancing guidelines were adhered to. Works were undertaken in Acocks Green town centre, Sutton Coldfield town centre Erdington town centre and within Birmingham City Centre. Civils works consisted of; relocating existing street furniture to create clear walkways, installation of temporary bollards to provide additional queueing capacity for retail premises and the installation of advisory signs and posts. Extensive temporary spray markings were installed as part of the works including; segregated pedestrian walkways, demarcated retail queueing areas, 2m spacing footprint markings into retail premises and COVID-19 advisory text markings. All temporary markings were undertaken as night works, when pedestrian flows were lowest.

Contract value
Client:
Birmingham City Council
Completion Date:
June 2020
Project:
COVID-19 Social Distancing Assistance Package
An assistance package for bars and restaurants within the city centre to effectively operate whilst observing social distancing guidelines; Birmingham City Council provided businesses the opportunity to utilise the footway to setup tables, chairs and canopies in order to help their trade. Parade Civil Engineering worked closely with the Client to generate design solutions and create viable options to re-route pedestrian flows. Upon successful design, a number of build-outs and bollard-lined pedestrian walkways with dropped crossing facilities were constructed. Works were delivered for the Jewellery Quarter BID Team and the Colmore BID Team.

Contract value
Client:
Birmingham City Council
Completion Date:
October 2020
Project:
Digbeth Controlled Parking Scheme
The city centre scheme consisted of the installation of parking bays, loading bays and double yellow carriageway markings on a large network of roads within Digbeth Business Quarter. Over 600 signs and posts were installed to facilitate the permit parking system. Due to heavy commuter parking and vehicular traffic during the working day, all road marking works were undertaken as night works over a period of 12 weeks. Similarly, due to high volumes of pedestrian commuter flows, civils works were carried out in a phased manner during off peak weekday hours.

Contract value
Client:
Birmingham City Council
Completion Date:
May 2020
Project:
Clean Air Zone – Variable Messaging Signs Scheme
The VMS Scheme was a part of the early measures package for Birmingham City Council’s Clean Air Zone project. Ten locations were identified along key commuter routes into the City as prime locations were motorists could be informed of congestion charges / messages in advance of entering the Clean Air Zone. Works involved; investigative works within the footway, supply and installation of wide base posts, installation of electric ducts, private electrical connections, electric upgrades and testing, and liaising with PDS Limited for the installation of the Variable Messaging Signs. The scheme was completed within budget and ahead of schedule.

Contract value
Client:
Birmingham City Council
Completion Date:
April 2020
Project:
Bromsgrove Cycle Route
The scheme was part of a package of works to be delivered in Bromsgrove which aimed to improve pedestrian / cycle transport infrastructure and promote safe cycle use to the local community. The works consisted of reconstructing the existing footway along Stoke Road to a 3 metre width creating a shared use footway for pedestrians and cyclists. Civils operations involved; kerbing, drainage, footway reconstruction and landscaping. Due to the location of the works, a temporary one-way traffic flow and diversion system was installed and maintained until completion, this enabled the scheme to be delivered ahead of programme.

Contract value
Client:
Worcestershire County Council
Completion Date:
November 2019
Project:
Parsons Hill Traffic Signal Scheme
The scheme was part of a package of works to be delivered in Bromsgrove which aimed to improve pedestrian / cycle transport infrastructure and promote safe cycle use to the local community. The works consisted of reconstructing the existing footway along Stoke Road to a 3 metre width creating a shared use footway for pedestrians and cyclists. Civils operations involved; kerbing, drainage, footway reconstruction and landscaping. Due to the location of the works, a temporary one-way traffic flow and diversion system was installed and maintained until completion, this enabled the scheme to be delivered ahead of programme.

Contract value
Client:
Birmingham City Council / Bellway Homes
Completion Date:
April 2019
Project:
Belchers Lane Local Safety Scheme
A local safety scheme to improve the traffic flows and crossing facilities at an existing roundabout junction on Belchers Lane. Being located within the vicinity of a hospital, local schools, residential properties and a number commercial food outlets, works were undertaken during off-peak restricted hours. Works consisted of; remodelling the existing crossing points to the pedestrian flows better, upgrading an existing zebra crossing, removal of a number of trees to maximise pedestrian visibility, installation of pedestrian guardrail, anti-skid surface treatment and carriageway markings.

Contract value
Client:
Birmingham City Council
Completion Date:
December 2018
Project:
Paradise Circus Regeneration Scheme – Designated Bus Lane
As part of the Paradise Circus Urban Regeneration Scheme in Birmingham City Centre, Parade Civil Engineering Limited were appointed to carryout road marking and civils works on A4400 Great Charles Street. Works consisted of amending existing road markings to implement a designated bus lane, the construction of several build-outs in high quality granite products, ducting works for electrical connections, installation of posts, signs and Vehicle Activated Signs (VAS). Due to heavy vehicular traffic and high levels of pedestrian flows in the City Centre these works were commissioned as night time working only.

Contract value
Client:
Birmingham City Council
Completion Date:
May 2018
Project:
Birmingham Cycle Revolution – City Centre Cycle Parking
An innovative scheme designed and delivered by Birmingham City Council as part of the Birmingham Cycle Revolution, with the aim of providing additional cycle parking and cycle maintenance facilities within the City Centre. The scheme consisted of installing bespoke styled bike ports, cycle racks, cycle stands and cycle maintenance stations within a number of prime locations throughout Birmingham City Centre.

Contract value
Client:
Birmingham City Council
Completion Date:
February 2018
Project:
Dudley Street Public Enhancement Scheme
The aim of the scheme was to improve the street scene of Wolverhampton City Centre’s High Street, a busy commercial area in the City Centre with high pedestrian flows and a number of high profile shop frontages. The scheme consisted of upgrading existing carriageway and footways with high quality granite paving materials, carriageway surfacing in buff SMA, imprint and road marking works, installation of tree pits and street furniture including a bespoke cycle shelter, cycle stands, benches, bins and bollards.

Contract value
Client:
Wolverhampton City Council
Completion Date:
September 2017
Project:
Warwick Road / Stockfield Road Signalised Junction
A major upgrade of this busy signalised offset junction on one of the City’s main arterials involved the provision of two new Toucans linked to the existing traffic controller and included traffic signage, ducting and cabling, furniture, pedestrian refuges and road markings.

Contract value
Client:
Birmingham City Council
Completion Date:
August 2017
Project:
Cannon Hill Nature Centre Car Park
The scheme consisted of constructing a 1450m2 car park within a four week time period, in advance of the School summer holidays. Works included earthworks, surveying and levelling, drainage, construction of soakaways and inspection chambers, kerbing and paving works, carriageway and footway construction, landscaping, installation of timber trip rail, street lighting, commissioning of parking meters and road marking works.

Contract value
Client:
Birmingham City Council
Completion Date:
May 2017
Project:
Caroline Street Enhancement Scheme, Jewellery Quarter
Part of the City’s capital programme, the scheme involved the construction of a new tree lined central reservation in high quality stone paving together with junction entry upgrades in matching stone setts and included, traffic signage, furniture and road markings. The works location in a busy business precinct of the City’s Jewellery quarter required extensive consultations with all Stakeholders in order to provide a safe environment for road workers and users with the minimum of disruption.

Contract value
Client:
Birmingham City Council & JQ BID Team
Completion Date:
February 2017
Project:
Shaftsbury Square Car Park
The scheme was delivered by the Local Authority and the Housing Association in order to provide local residents with car parking facilities. Works consisted of removing a number of mature trees, constructing a car parking area using grass grid paving, construction of footpaths and landscaping.

Contract value
Client:
Sandwell Metropolitan Borough Council
Completion Date:
October 2016
Project:
Interconnect Wayfinding Totems Phase 1 & Phase 2
This was the second phase we undertook as part of the City’s programme for the provision of illuminated wayfinding Totems. Our works included taking delivery and erection of the units on preformed foundations together with providing them with electrical power. The locations were all within the busy City Centre roads or the canal towpaths which caused difficulties with access and the traffic management of pedestrians.

Contract value
Client:
Marketing Birmingham
Completion Date:
March 2016
Project:
LSTF Pershore Road Corridor
A major part of the City’s ongoing Cycle Route programme, the project involved a series of schemes along the A441 Pershore Road Corridor from Belgrave Interchange to Kings Norton Green. The works included implementation of bus lanes, ten signalised pedestrian crossing upgrades, build outs, pedestrian refuges, extensive signage, and road marking amendments.

Contract value
Client:
Birmingham City Council
Completion Date:
May 2015
Project:
Cotteridge Local Centre
The Cotteridge Local Centre scheme was part of the City’s Capital Budget and carried out at the same time as the Selly Oak Local Centre scheme. Both schemes were similar in nature and location; busy shopping precincts with upgraded Bus Interchanges and new signalised pedestrian crossings required similar solutions to minimise disruptions to highway users, local businesses and bus companies. Shop frontages were rekerbed and repaved with bright modular elements to create additional parking and improved access for shoppers.

Contract value
Client:
Birmingham City Council
Completion Date:
March 2015
Project:
Shenley Field Junction Improvements
The scheme consisted of upgrading a busy crossroads junction in Selly Oak to a continental style roundabout, which aimed at reducing the number of vehicular / cyclist accidents. The works consisted of constructing a roundabout with pedestrian refuges, ducting and drainage, carriageway planing and resurfacing, organising electrical connections and disconnections, and maintaining vehicular and pedestrian traffic management throughout the scheme.

Contract value
Client:
Birmingham City Council
Completion Date:
October 2014
Project:
Sandwell Lighting Upgrade
The scheme was an early section of the Borough’s programme for upgrading all street lighting to LED and the installation of CMS nodes to facilitate remote monitoring and control. The works involved the replacement of 220 No. existing street lighting lanterns on a point for point basis on roads within the Borough of Sandwell, and included: structural visual inspection, replacement of lanterns, installation of nodes, electrical certificate, provision of manufacturer’s warranty for the lanterns and data to implement CMS control.

Contract value
Client:
Sandwell Metropolitan Borough Council
Completion Date:
June 2014
ACCREDIATIONS
